Oracle OM promise date calculations


How is the Schedule Ship Date calculated? 
Non-ATP: set to Request Date
ATP: uses calendars, supply and demand, 
Using Advanced Supply Chain Planning, supply/demand is set up at the plan level.
Global Order Promising will only use the infinite time fence specified on the ATP rule.
 
• How is the Schedule Arrival Date calculated?    
Calculated based on Scheduled Date plus the time required for shipping from the warehouse to the customer location via a specified ship method.
The shipping network must be defined.
 
• How does Schedule Ship Date and Promise Date get calculated?
• How to let the Schedule Ship Date be same as Promise Date?
Both are controlled by the System Parameter Promise Date Setup.
*First Schedule Ship Date - Schedule Ship Date or Schedule Arrival Date will be copied to the Promise Date when line is first scheduled.
The Promise Date will not be changed for subsequent  scheduling actions.
 
 First Request Date - Promise Date will be copied with first request date.
The Promise Date will not be re-defaulted after the first time.
 
 Manual – Either  manually enter whatever Promise Date you choose or default Promise Date.
 Schedule Ship Date – Either Schedule Ship Date or Schedule Arrival Date will be copied to the   Promise Date.
If the Schedule Ship Date or Schedule Arrival Date are updated, the Promise Date will also be updated.
 
 Request Date - Request Date will be copied to the Promise Date for every change in the Request Date.
A change to the Request Date will be reflected in the Promise Date.
 