Ship set

How Schedule Ship date will be calculated when Ship Set Applied?


Example of Supply Details
Item On Hand Supply Date Infinite Supply = 6 months Latest Acceptable Date = 7 months
A 20 27 Sept 2017      120 days 140 days
B 100 27 Sept 2017      120 days 140 days
C 10 WIP order on 20 Nov 2017      120 days 140 days
D 0 No supply scheduled = infinite 120 days 140 days
For order 123:
  • No Ship Set is entered manually on the lines at the time of order entry.
  • When saving, the system assigns and populates the Ship Set Name.
  • The system looks at ATP availability for all order lines when ATP is applicable, and schedules the order lines for the Ship Set to the latest acceptable ATP date.
  • If scheduling fails to meet a common date then the order lines are saved, but will not scheduled or assigned to a Ship Set. (This occurs only if the Latest Acceptable Date does not exceed the Infinite Supply Time Fence)
The scheduling details for order 123, after the initial save was performed are displayed within the following table.
Example of Save Performed
Order Line Item Qty Request Date Schedule Date Ship Set
1 A 20 27-Sep-2017       2-Oct-2017          1
2 B 20 27-Sep-2017       2-Oct-2017          1
3 C 20 27-Sep-2017       2-Oct-2017           1
4 D 20 27-Sep-2017        2-Oct-2017          1
Now, if two additional lines are added to the order, the system will assign and populate the Ship Set, once the order is saved.
The system again verifies ATP availability, and will auto push the entire group (order lines), scheduling the lines for the Ship Set to the latest ATP date. If scheduling fails to meet a common date then the two new lines will be saved, are not scheduled, and will not be assigned to a Ship Set (Latest Acceptable Date is greater than the Infinite Time Fence).
The following table displays the scheduling results after adding two additional order lines.
Example of Scheduling Results
Order Line Item Qty Request Date Schedule Date Ship Set
1 A 20 27-Sep-2017       2-Oct-2017    1
2 B 20 27-Sep-2017         2-Oct-2017         1
3 C 20 27-Sep-2017        2-Oct-2017         1
4 D 20 27-Sep-2017        2-Oct-2017         1
5 D 20 27-Sep-2017        2-Oct-2017          1
6 D 20 27-Sep-2017        2-Oct-2017          1


If the item D is now available for Sept 29, 2017,.
Example Status Results
Order Line Item Qty Request Date Schedule Date Ship Set
1 A 20 27-Sep-2017       Sept 29, 2017       1
2 B 20 27-Sep-2017      Sept 29, 2017       1
3 C 20 27-Sep-2017      Sept 29, 2017       1
4 D 20 27-Sep-2017       Sept 29, 2017       1
5 D 20 27-Sep-2017      Sept 29, 2017       1
6 D 20 27-Sep-2017      Sept 29, 2017       1

 